Student Center - PHASE II
Task |
Start |
Finish |
| Bldg G, Computer Lab/ new General Store/ SRTV | 06/05/06 |
02/13/07 |
| Bldg F, Food Co-op/ Bike Shop | 07/03/06 |
12/15/06 |
| Bldg E, Lecture Notes/ Soft Reserves | 07/12/06 |
11/10/06 |
| Bldg C, KSDT/ ATMs- new location | 07/17/06 |
10/27/06 |
| East Site work | 11/03/06 |
01/04/07 |
| Bldg D, North Conference Rm/ ATMs/ Storage | 02/09/07 |
02/28/07 |
| Bldg H, New Groundwork/ Student Services/ Grove Seating / Classroom | 02/26/07 |
06/27/07 |
| West and Central Site work | 04/13/07 |
09/20/07 |
Price Center
| Task | Start |
Finish |
|---|---|---|
| Price Center / Bookstore Expansion | 05/06 |
03/08 |