Construction Updates

Student Center - PHASE II

Task
Start
Finish
Bldg G, Computer Lab/ new General Store/ SRTV
06/05/06
02/13/07
Bldg F, Food Co-op/ Bike Shop
07/03/06
12/15/06
Bldg E, Lecture Notes/ Soft Reserves
07/12/06
11/10/06
Bldg C, KSDT/ ATMs- new location
07/17/06
10/27/06
East Site work
11/03/06
01/04/07
Bldg D, North Conference Rm/ ATMs/ Storage
02/09/07
02/28/07
Bldg H, New Groundwork/ Student Services/ Grove Seating / Classroom
02/26/07
06/27/07
West and Central Site work
04/13/07
09/20/07

 

Price Center

Task
Start
Finish
Price Center / Bookstore Expansion
05/06
03/08

 